the drainage channel of Dunga Nallah having appx. 1.5 meter width and 16 meter height. |
b.) Retaining structure provided in the slope of mine adjacent to road in |
| course of Dunga Nallah having |
| appx. 1.5 meter width and 6 meter |
| height. |
| c.) Parapet retaining structures are |
| provided across five benches of |
mine having appx. 0.5 meter width and 1 meter height. |
The photographs of retaining |
structures provided are attached as Annexure-R1/1. |
| Complainant Sh. Dinesh Kumar |
| who was present at the site also |
| acknowledged the work carried out |
| by M/s Bohar Lime Stone mine of |
| Jai Singh Thakur & Sons and given |
| his written statement regarding |
| satisfactory work to protect the |
| debris flowing into Nallah and has |
no objection regarding operation of
|
| the limestone mine. The written |
statement of complainant Sh. |
Dinesh Kumar is attached as |
| Annexure-R1/2. |
| (ii) M/s Balbir Singh Supa Ram: - |
| The repair and maintenance work of |
| retaining wall structures has not |
| been initiated till date. The mine is |
non-operational since 24 June |
| 2023. A letter was issued by |
| HPSPCB Paonta Sabib vide letter |
| No. 2871-76 dated 12.11.2024 to |
| the mine owners to submit status of |
completion of work as per |
recommendations of the Joint |
| Committee. (Annexure R1/3). M/s |
| Balbir Singh Supa Ram submitted |
| reply and given undertaking vide |
letter dated 15.11.2024 that |
limestone mine was non- |
| operational. Copy of reply submitted |