Inderjit Mehta Constructions Pvt. Ltd. v. Union of India
Case brief
What is this about?
The High Court allowed a petition under Section 29A(4) & (5) of the Arbitration and Conciliation Act, 1996, extending the arbitral tribunal's mandate by three months to 30.09.2025, finding sufficient cause due to the arbitrator's office shifting.
What did the court decide?
Mandate of the Arbitral Tribunal extended for three months to 30.09.2025; period from 31.05.2025 regularised.