Universal Agency Ramgarh Pvt. Ltd. v. Prl Projects and Infrastructure Ltd.
Case brief
What is this about?
Petition sought extension of the Arbitral Tribunal's mandate under Section 29A as arbitration was at final stage of arguments. Finding sufficient cause explained, the court extended the mandate by six months, regularised the period from 30.09.2024, and disposed of the petition with pending applications.