Petition under Section 29A(4) sought a one-year extension of the arbitral tribunal's mandate, proceedings being at the evidence stage. The court found sufficient cause explained and extended the mandate from 11.08.2024 to 10.08.2025, regularising the intervening period.
What did the court decide?
Mandate of Arbitral Tribunal extended by 1 year from 11.08.2024 to 10.08.2025; interim period regularised.