M/S Fitness for India v. M/S Suridhi Commercial Infra Pvt. Ltd.
Case brief
What is this about?
The Delhi High Court allowed an extension of time for completing arbitral proceedings and making the award under Section 29A(4) of the Arbitration and Conciliation Act, 1996, till 30.09.2025.
What did the court decide?
Extension of time for completion of arbitral proceedings and making of arbitral award till 30.09.2025 allowed.