B.D. Raizada Projects Pvt. Ltd. v. Union of India
Case brief
What is this about?
The Delhi High Court allowed a petition seeking extension of the arbitrator's mandate under Section 29A of the Arbitration and Conciliation Act, 1996. The court ruled that since the proceedings were concluded and only the award remained, the mandate was extended by six months.
What did the court decide?
Extension of the Arbitral Tribunal's mandate for a period of six months till 20.06.2024.