Petition under section 29A(4) and (5) of the Arbitration & Conciliation Act 1996 sought a six-month extension of the arbitral tribunal's mandate. The respondent did not object. The court extended the mandate by six months and validated steps taken during the expired period.
What did the court decide?
Mandate of Arbitral Tribunal extended by six months; past steps in the arbitral process validated and regularised.