that the Respondent floated a tender for the work of "Construction of 2 laning with paved shoulder of new Greenfield alignment from Chochenpheri at Km. 52.000 to Helipad near Menla at Km. 82.000 of Rhenoc-Menla spur (NH-717 B) Package-III on EPC basis under SARDP-NE Phase 'A' in the State of Sikkim". The Petitioner was the successful bidder and the Petitioner was offered the work. The Respondent by a letter dated 28.10.2020 gave its acceptance to the Petitioner for the contract at a bid price of Rs.532,52,00,000/-. In pursuance of the terms of the bid document, the Petitioner furnished the performance security of Rs.26,62,60,000/- and an additional performance security of Rs.3,16,82,000/- as per clause 2.21 of the RFP. The appointed date of the project was declared as 10.12.2020 and the work was to be completed within 36 months from the said date. The Petitioner started the work. Various disputes has arisen between the Petitioner and the Respondent as to whether the Petitioner has been given the Right of Way (ROW) for the performance of the work or not.