Khairipura-Binaki Mangalwari Premnagar Niwasi Action Committee Thr. Its President v. the Union of India Thr. Its Secty. and Ors.
Case brief
What is this about?
The Respondents implemented a meeting decision to construct a new Railway under Bridge and remove encroachments. The Court, satisfied that the petitioner's concerns are addressed, dismissed the petition with specific directions for completion timelines.
What did the court decide?
Directions to construct Railway Under Bridge in 18 months, remove encroachments in a fortnight, maintain storm water arrangements, and close level crossing after new RuB operational.