Rongali Gangathalli v. State of Andhra Pradesh
Case brief
What is this about?
The High Court of Andhra Pradesh disposed of a writ petition filed by a contractor seeking direction to release unpaid amounts for school repair and construction works. The court directed the State Project Director to release an admitted sum of Rs. 7,36,704/ within three months.
What did the court decide?
Directed respondent No. 3 to release Rs. 7,36,704/- to the petitioner as expeditiously as possible, within three months from the date of receipt of the order.