M/S.Suguna Metals Pvt.Ltd v. the M.D., Apcpdcl., and 3 Others
Case brief
What is this about?
Petitioner challenged revised electricity bills for September to November 2013 that failed to credit energy availed under Open Access. Without going into merits, the court permitted a fresh representation to the respondents and directed them to pass appropriate orders within two months after hearing the petitioner.