This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
THE HON'BLE SRI JUSTICE A.V. SESHA SAI
W.P.No.1457 of 2009
Between:
Aditya Engineering Works Rep. by Managing Partner, K Srrihari Raju
PETITIONER
AND
1. The Assistant Labour Commissioner (Central) Visakhapatnam, Visakhapatnam District, and others.
RESPONDENTS
ORDER:
It is represented by Sri K. Ananda Rao, learned counsel for the petitioner that the cause in the writ petition does not survive for adjudication and the writ petition has become infructuous.
Recording the said submission, this writ petition is dismissed as infructuous. No order as to costs. As a sequel, the miscellaneous petitions, if any, shall stand closed.
_______________________ JUSTICE A.V. SESHA SAI.
19th September, 2014 Js.