Swarna Enterprises v. The State Of Bihar and Ors.
Case brief
What is this about?
The Court allowed a petitioner whose electric connection was disconnected due to alleged energy theft. It directed the petitioner to deposit 50% of the provisionally assessed loss within two weeks from a specific date, upon which the respondent must restore the connection within 48 hours. The arrangement remains effective until the final assessment of loss.
What did the court decide?
Direction to deposit 50% of provisionally assessed loss within two weeks and restore electric connection within 48 hours thereof.