Umesh Prasad v. The Bihar State P
Case brief
What is this about?
Allowed deposit of 50% assessed loss for restoration of electric connection pending appeal against assessment order.
What did the court decide?
Petitioner directed to deposit 50% of loss amount; connection to be restored within 48 hours.
What the court decided
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.2184 of 2014
====================================================== 1. Umesh Prasad Son Of Late Geeta Prasad Resident Of MohallaMachharhatta, P.S.- Barh, District- Patna .... .... Petitioner/s Versus 1. The Bihar State Power Holding Company Limited Through Its Managing Director, South Bihar, Vidyut Bhawan, Bailey Road, Patna 2. The Electrical Executive Engineer, Electric Supply, Barh 3. The Electrical Assistant Engineer, Electric Supply Sub-Division, Barh 4. The Electrical Junior Engineer, Electric Supply Branch, Barh Urban .... .... Respondent/s ====================================================== Appearance : For the Petitioner/s : Mr. Mani Bhushan Kumar For the Respondent/s : Mr. Vinay Kirti Singh ====================================================== CORAM: HONOURABLE MR. JUSTICE KISHORE KUMAR MANDAL ORAL ORDER
2 04-03-2014 Heard Mr. Mani Bhushan Kumar for the petitioner and Mr. Vinay Kirti Singh for the respondent South Bihar Power Distribution Company Ltd (for short “ the Company”).
As prayed by learned counsel for the petitioner, let appropriate correction in the name of the respondent no. 1 be made in course of the day.
The petitioner is L.T.I.S. consumer of the respondent Company. Electric connection vide No. 1220611 BH-5238 of 7.5 H.P. load was installed in the Flour Mill of the petitioner. An inspection was carried out by the team of officials of the respondent Company on 24.12.2013 wherein the petitioner was found engaged in commission of theft of energy by resorting to
Patna High Court CWJC No.2184 of 2014 (2) dt.04-03-2014
Issues for consideration
1 issue framed by the court
Whether the petitioner can be allowed to restore connection upon depositing 50% loss amount pending appeal.
Parties & counsel
- petitioner
Umesh Prasad
- respondent
Bihar State Power Holding Company Limited
Coram
Kishore Kumar Mandal
Case details
As recorded by the court registry