Single Judge disposed of Writ Petition No. 455 of 2021, directing the respondent to consider a representation for early completion of a project and pass an order within three months.
What did the court decide?
Direction to the respondent to consider the representation filed by the petitioner and pass appropriate orders within three months.
What the court decided
A compact analysis
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
W.P.(C) No. 455 of 2021
- 12.01.2021 The matter is taken up through video conferencing. Heard Mr. K.K. Mishra, learned counsel for the petitioner.
The petitioner has filed this writ petition seeking direction to the opposite party no.1 to ensure early completion of proposed work through opposite party no.3 or through any other contractor having experience to do so.
In course of hearing, learned counsel for the petitioner states that highlighting the grievance, the petitioner has made representation to the opposite party no.1 vide Annexure-2, and direction be given to the said opposite party to consider and dispose of the same.
In view of the aforesaid limited grievance of the petitioner, this Court disposes of the writ petition directing the opposite party no.1 to take a decision on the representation filed by the petitioner vide Annexure-2 and pass appropriate order in accordance with law within a period of three months from the date of production of certified/ authenticated copy of this order by the petitioner.
As COVID-19 pandemic situation is continuing, learned counsel for the parties may utilize the soft copy of this order available in the High Court’s official website or print out thereof at par with certified copies in the manner prescribed vide Court’s Notice No.4587 dated 25.03.2020.
…………….…………… (DR. B.R. SARANGI) JUDGE
GDS
Issues for consideration
1 issue framed by the court
Whether the respondent state authority shall be directed to consider a representation filed by the petitioner for early completion of proposed work.
Parties & counsel
- petitioner
Petitioner
- respondent
Opposite Party No.1
Coram
Dr. B.R. Sarangi
Case details
As recorded by the court registry
Similar cases
Judgements on the same questions, provisions and authorities, from every court