Madhukar Vishnu Gaikwad v. Ministry of Environment Forest and Climate Change
Case brief
What is this about?
The Tribunal addressed an application regarding discharge of untreated effluent by M/s Shivneri Sugar Ltd. Finding that the industry was in violation between late November 2024 and mid-April 2025, the Tribunal directed the MPCB to calculate and recover an environmental compensation amount for the specific period from November 20, 2024 to April 3, 2025.
What did the court decide?
MPCB directed to calculate and levy EDC from M/s Shivneri Sugar Ltd. for period from 20.11.2024 to 03.04.2025 within one month.