tender process is complete in all respects, and the tanker lorries have already been inducted and since the petitioners are also running tanker lorries consequent to the Letter Of Intent issued, they cannot be said to be aggrieved in any manner. It is also submitted that, the terms and conditions of all Letter Of Intent/work order are identical as specified in Ext.P2, and on a perusal of Clause 10 of Ext.P2 will show that the Bank Guarantee and the Security Deposit are to be submitted within 15 days of receipt of Letter Of Intent/work orders, and in Clause 22 of Ext.P2, it is mentioned that the tanker lorries shall be physically placed within 30 days of receipt of Letter Of Intent/work order. It is also submitted that, the party respondent viz., A.M. David has received the Letter Of Intent on 02.02.2019 and submitted the Bank Guarantee on 05.02.2019 and signed the agreement. Likewise, M/s.