Asok Kumar v. Superintending Engineer
Case brief
What is this about?
In this writ petition, a petitioner contractor challenged the termination of his work contract by the Superintending Engineer due to delayed execution. The contractor claimed delay was caused by pending pollution control consent. The Court held the contract was not statutory and dismissed the petition, directing the petitioner to approach the civil court.