Joseph Mathew v. Superintending Engineer
Case brief
What is this about?
This writ petition challenges delayed payment of a final bill for construction of a culvert and drain. The court directed the State to issue a letter of credit and pay the petitioner expeditiously, setting an outer limit of three months.
What did the court decide?
Direction to the State of Kerala to issue a letter of credit and effect payment to the petitioner expeditiously, within three months of producing the certified judgment copy.