2. An auction was conducted by the respondents-State for allotment of different Sand Ghats. One of the Sand Ghats , situated at Mauja Furberiya Panchayat Under Plot No 1538, 833, 1193 over an of 46.50 acres on the Bank of Barakar River, District Jamtara was also auctioned and the petitioner was declared as the successful bidder. Letter of intent provided that the petitioner was required to get the mining plan approved and also get the environmental clearance. Petitioner applied for grant of environmental clearance. As per the petitioner, vide a letter dated 25.01.2016, respondents acknowledged that the process of obtaining environmental clearance is cumbersome and it consumes lot of time, as such the lease period of three years would be reckoned from the date of agreement. Petitioner took steps to obtain environmental clearance and for approval of mining plan. Though the mining plan was approved on 13.07.2015 , the State Level Environmental Impact Assessment Authority issued environmental clearance, after three years, i.e., vide order dated 5th June, 2018. The petitioner applied for execution of the lease/ agreement, but the same was not executed on the ground that environmental clearance was not obtained within 180 days. Admittedly, as the petitioner could obtain the environmental clearance after 180 days, the letter of intent was cancelled. As there was no fault on the part of the petitioner in obtaining environmental clearance and it is because of the respondents that the environmental clearance was granted after 180 days, the petitioner filed a revision application under Rule 62 of the Jharkhand Minor Mineral Concession Rules, 2004 before the Mines Commissioner. The Mines Commissioner, vide an order dated 16.12.2019 in Revision Case No 75/2018 held that the petitioner was not responsible for the delay in submitting the environmental clearance, hence, delay cannot be attributed to the petitioner. The order by which the letter of intent was cancelled, was set aside and the matter was remanded to the Deputy Commissioner, Jamtara to pass a fresh order after giving opportunity of hearing to the petitioner. Ultimately, on 20th February, 2020, after the order was passed by the Mines Commissioner, the respondent State executed an agreement, wherein the Sand Ghat was allotted to the petitioner for a period of three years from the date of agreement, i.e., 20th February, 2020 to 19th February, 2023. The petitioner obtained environmental clearance from the Pollution Control Board including consent to establish and consent tooperate. The petitioner started operating the Sand Ghat by excavating sand. Further