Shokat Ali v. Ut of J and K Th Commissioner Secretary Pw Deptt and Others
Case brief
What is this about?
Release of payment; admitted liability; JCB and Tipper engaged for road restoration; Special Sub-Division Gandoh; PWD (R&B) Doda; Chief Engineer PW (R&B) Chenab Zone Batote; Executive Engineer PWD (R&B) Gandoh; UT of Jammu and Kashmir; Commissioner/Secretary PW (R&B) Department; bills/invoices raised after completion of works; repeated representations and reminders; interdepartmental communication dated 16.03.2019; Rs. 20,00,000/- Rupees twenty lacs; Rs. 20.00 lacs; interest at prevailing bank rate; direction to consider and decide claim; two months from certified copy; release within two weeks of decision; decision to be conveyed to petitioner; disposed of along with all CMs; Shokat Ali; Ahtisham Hussain Advocate; Justice Moksha Khajuria Kazmi; Jammu; 17.11.2025; WP(C) No.3192/2025.
What did the court decide?
Petition disposed of at its threshold with a direction to the respondents to consider and decide the petitioner's claim within two months from furnishing of a certified copy of the order; if found entitled, the amount is to be released within two weeks of the decision, and the decision conveyed to the petitioner.