M/S Kohli Construction Th Proprietor Mohd Munshi v. Ut of J and K Th Commissioner Secretary to Govt. Power Development Department and Others
Case brief
What is this about?
WP (C) 3172/2025; Kohli Construction; Mohd. Munshi; JPDCL Kishtwar; Jammu Power Distribution; release of payment; Rs. 27,82,663; 24% interest; JJM scheme; turnkey works; WSS Kote Top; WSS Kuluthan; WSS Batogra; admitted liability; non-availability of funds; direction to consider claim; two months; disposed of at threshold; Moksha Khajuria Kazmi; 14.11.2025.
What did the court decide?
Direction to the respondents to consider the petitioner's claim (release of Rs. 27,82,663/- with interest @24% per annum) and take a decision within two months of the certified copy being furnished, subject to verification of requisite bills, with the decision to be conveyed to the petitioner; no immediate monetary relief ordered. ¶¶30