This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
IN THE DEBTS RECOVERY APPELLATE TRIBUNAL AT KOLKATA
(Dy. No. 635 of 2021)
(Arising out of S.A. No. 98 of 2019 in DRT-1 Hyderabad)
THE HON’BLE MR. JUSTICE ANIL KUMAR SRIVASTAVA
CHAIRPERSON
| 03.02.2023 | |
|---|---|
| M/s Siddhi Vinayak Industries … Appellant -Vs- |
|
| Central Bank of India & ors ….Respondents |
|
| Mr. Debasish Chakrabarty, Learned Counsel, Mr. Rahul Auddy, Learned Counsel, Mr. |
|
| Aditya Gupta, Learned Counsel for the Appellant |
|
| Mr. P.K. Mukherjee, Learned | |
| Counsel for the Respondent |
THE APPELLATE TRIBUNAL :
Learned Counsel for the Appellant prays for and granted a weeks time to file an application for condonation of delay. He may file the Application with copy to the Respondent who may file objection if any, within a week thereafter.
List on 23rd March, 2023.
Parties & counsel
- appellant
M/s Siddhi Vinayak Industries
- respondent
Central Bank of India & ors
Coram
Anil Kumar Srivastava
Case details
As recorded by the court registry
All orders in this case
12 orders share this CNR
Similar cases