Ramesh Kumar Ranaik v. M/S Shyam Indus Power Solutions Pvt. Ltd.
Case brief
What is this about?
Section 29A petition seeking extension of time to conclude arbitration proceedings. Respondent raised no serious objection. Court extended the period for conclusion of proceedings by six months and disposed of the petition along with the pending application.
What did the court decide?
Time for conclusion of arbitration proceedings extended by six months.