Dee Vee Projects Ltd. v. Hindustan Urvarak and Rasayan Ltd.
Case brief
What is this about?
Petition under Section 29A of the Arbitration & Conciliation Act, 1996 sought extension of time to conclude arbitration proceedings; respondent counsel raised no serious objection. The court extended the period by two weeks as prayed and disposed of the petition.
What did the court decide?
Time period for conclusion of arbitration proceedings extended by two weeks, as prayed for.