Srico Projects Pvt. Ltd. v. Central Railside Warehouse Co. Ltd.
Arbitration & Conciliation Act, 1996 – Section 29A – Extension of time for concluding arbitration proceedings
Case brief
What is this about?
Delhi High Court, O.M.P.(MISC.)(COMM.) 163/2026 (with I.A. 3899/2026 & I.A. 3900/2026), SRICO PROJECTS PVT. LTD. v. CENTRAL RAILSIDE WAREHOUSE CO. LTD., decided 12.02.2026 by Justice Avneesh Jhingan. Petition under Section 29A of the Arbitration & Conciliation Act, 1996 for extension of period to conclude arbitration proceedings; respondent raised no objection; extension of one year granted; petition disposed of.
What did the court decide?
Period for conclusion of the arbitration proceedings extended by one year. ¶15