Vm Construction v. Union of India
Case brief
What is this about?
Petition under Section 29A(4) of the Arbitration and Conciliation Act sought extension of the arbitral mandate in Arbitration Case No. DIAC/2701/01-20. The court allowed the petition and extended the arbitration period by nine months from 08.11.2024.
What did the court decide?
Period of Arbitration Case No. DIAC/2701/01-20 extended by nine months from 08.11.2024.