Hs Oberoi Buildtech Prn Ate Limited v. Mahamaya Infrastructure Pvt. Ltd.
Case brief
What is this about?
Section 29A(4) Arbitration and Conciliation Act 1996; extension of arbitral mandate; expired arbitrator mandate 07.11.2023; sufficient cause for delay; post-expiry mediation failed; tribunal continued proceedings with voluntary participation; period regularisation; O.M.P.(MISC.)(COMM.) 267/2025; Delhi High Court; Jasmeet Singh, J.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal by a period of six months from 07.05.2025 to conclude the arbitral proceeding and make the arbitral award, with the period from 07.11.2023 till the order date regularised. ¶8