Pma Construction Co. v. Ministry of Road Transport and Highways
Case brief
What is this about?
PMA Construction Co v Ministry of Road Transport and Highways, O.M.P.(MISC.)(COMM.) 823/2025, Delhi High Court, Justice Purushaindra Kumar Kaurav, order dated 19.11.2025: arbitrator's mandate extended by six months with consent of parties; period from 15.04.2025 regularized; petition disposed of. No statutes or precedents discussed.
What did the court decide?
Extension of the arbitrator's mandate for six months from the date of the order, and regularization of the period from 15.04.2025 till the date of the order. ¶14