Reliance Infrastructure Limited v. Madhyanchal Vidyut Vitran Nigam Limited
Case brief
What is this about?
Petition under Section 29A sought a 30-day extension of the arbitral tribunal's mandate; the award had already been passed and only a clarification application was pending. Finding sufficient cause shown, the court extended the mandate by 30 days and regularized the interim period.
What did the court decide?
Mandate of the arbitral tribunal extended for 30 days to decide the Section 33 application; period from 19.09.2025 regularized.