Era Infra Engineering Ltd. v. Executive Engineer Public Works Department
Case brief
What is this about?
Petition under Section 29A(4) and (5) of the Arbitration and Conciliation Act, 1996 sought extension of the arbitral mandate, with proceedings at final arguments. With the respondent's consent, the Court extended the arbitrator's mandate by six months from 13.05.2025 and regularised the intervening period.
What did the court decide?
Mandate of the learned Arbitrator extended by six months from 13.05.2025; period from 31.08.2024 to 12.05.2025 regularised.