Malwa Solar Power Generation Private Limited v. M/S Vikram Solar Limited
Case brief
What is this about?
Single judge bench extended the mandate of an Arbitral Tribunal until 31 December 2024 under Section 29A(4) of the Arbitration and Conciliation Act 1996 after noting the respondent's consent.
What did the court decide?
Mandate of the Arbitral Tribunal extended till 31 December 2024.