Cinepolis India Pvt. Ltd. v. Alan Infratech Private Limited & Anr.
Case brief
What is this about?
Petition under Section 29A(4)&(5) of the Arbitration and Conciliation Act, 1996 seeking a six-month extension of the arbitral mandate, with rejoinder arguments pending. Counsel accepted notice without objection; the court found sufficient cause shown and extended the mandate by six months.
What did the court decide?
Mandate of the Arbitral Tribunal extended by 6 months to conclude proceedings and publish the award.