National Highways Authority of India v. Madurai Tuticorin Expressways Ltd.
Case brief
What is this about?
In this petition under Section 29A(5) of the Arbitration and Conciliation Act, 1996, the Court extended the mandate of the Arbitral Tribunal by nine months from the date of the order due to the expiry of its previous mandate, with no objection from the respondent.
What did the court decide?
Mandate of the Arbitral Tribunal extended by nine months from the date of the order, continuing from 31 July 2024.