Slipco Constructions Pvt. Ltd. v. Bharat Heavy Electricals Ltd.
Case brief
What is this about?
The Delhi High Court allowed the petitioner's petition under Section 29A of the Arbitration and Conciliation Act, 1996, extending the arbitral tribunal's mandate for eight months from 07.08.2024 with the parties' consent.
What did the court decide?
Extension of the mandate of the arbitral tribunal for a period of 8 months with effect from 07.08.2024.