Mep Chennai Bypass Toll Road Private Ltd. v. National Highways Authority of India & Anr.
Case brief
What is this about?
Petitioner sought extension of Arbitral Tribunal mandate under Section 29A(4) of the Arbitration and Conciliation Act, 1996. The court allowed the extension for ten days as agreed by respondents and since the award was ready.
What did the court decide?
Mandate of the Arbitral Tribunal extended for a period of ten days from today.