Montecarlo Limited v. Ministry of Road Transport and Highways
Case brief
What is this about?
Petition under Section 29(A) of the Arbitration and Conciliation Act sought extension of the arbitral tribunal's mandate in a NH-98 highway contract dispute. With final arguments concluded and only the award pending, the Delhi High Court extended the mandate by six months from 28 February 2024 and disposed of the petition.
What did the court decide?
Mandate of the Arbitral Tribunal extended by six months from 28.02.2024 to pronounce the award; petition and pending applications disposed of.