B.D. Raizada Projects Pvt. Ltd. v. Union of India through Chief Engineer Delhi Zone
Case brief
What is this about?
Petition under Section 29A seeking extension of the arbitral tribunal's mandate after parties concluded arguments. The court extended the mandate by six months from 20.06.2024, regularised the intervening period, and directed the arbitrator to list no further arguments.