Globe Civil Projects Pvt. Ltd. v. Union of India
Case brief
What is this about?
The Delhi High Court granted an extension of the sole arbitrator's mandate for three months effective 15.02.2024 under Section 29-A of the Arbitration and Conciliation Act, 1996. The court noted that arguments were concluded and the award was reserved, and the respondent had no objection to the extension.
What did the court decide?
The mandate of the learned Sole Arbitrator is extended for a further three months with effect from 15.02.2024.