The petitioners challenged the rejection of technical bids for road work tenders, arguing that 'consent to operate' was not required under the tender documents. The Court held that the NOC requirement implied 'consent to operate' and dismissed the petitions as the petitioner failed to submit the document after being given an opportunity to do so, noting that the tenders were already awarded.
What did the court decide?
The writ petitions and accompanying miscellaneous applications were dismissed.