Khandu Aaba Tambe and Others v. the State of Maharashtra through Its Secretary and Others
Case brief
What is this about?
Land acquisition by private negotiation (01.05.2005); delayed consent Award (09.11.2017); claim for rental compensation for possession-to-Award period based on Government Resolutions dated 01.12.1972 and 02.04.1979; rejection by acquiring authority (respondent No.3) on 22.03.2025 citing consent letters; Court holds consent letter limited to fair compensation; entitlement to rental compensation conceded by State through AGP; directions to calculate and pay rental compensation within one month; compliance date 10.03.2026; cost deposit on default; Section 80 RFCTLARR Act 2013 interest claim raised but not decided; neutral citation 2026:BHC-AUG:3700-DB; Bombay High Court, Aurangabad Bench; writ petition disposed.
What did the court decide?
Writ petition disposed of with directions: respondent No.3 to calculate rental compensation payable to the petitioners after hearing all necessary parties and to pay the determined amount within one month of determination; matter listed on 10.03.2026 for compliance, failing which the acquiring body is to be directed to deposit cost in the Court. The claim for interest under Section 80 of the RFCTLARR Act, 2013 was not expressly adjudicated in the order.