Sanjay Shantilal Gundecha v. the State of Maharashtra through Its Secretary and Others
Case brief
What is this about?
Writ petition disposed of with directions; petitioner-contractor Sanjay Shantilal Gundecha; tender under Mukhyamantri Gram Sadak Yojna; work order dated 01.07.2021; work completed but payment not given; proposals approved by respondent Nos. 3 and 4; representation dated 19.06.2025 pending with respondent No.1; direction to respondent No.1 to decide representation within two months; leave to amend granted; High Court of Judicature at Bombay, Aurangabad Bench; coram Smt. Vibha Kankanwadi and Hiten S. Venegavkar; dated 21st January, 2026; no statute or precedent cited; no quantum awarded.
What did the court decide?
Leave to amend granted (to be carried out immediately); respondent No.1 directed to respond to and decide the petitioner's representation dated 19.06.2025 within two months; with these directions the writ petition stands disposed of.