Ekta Muslim Vikas Sanstha , Kamothe v. City and Industrial Development Corp. of Maharashtra Ltd. (Cidco Ltd) and Ors.
Case brief
What is this about?
Bombay High Court common listing/order-scheduling order dated 02/12/2025, Coram Ravindra V. Ghuge & Ashwin D. Bhobe, JJ. Keywords: paucity of time; office objections removal two weeks; continuation of ad-interim/interim orders; affidavit in reply/rejoinder one week before next date; spare copies 14 days; dismissal against unserved respondents on 15th day; notice returnable four weeks; listing chart 09/12/2025 to 21/01/2026 (Fresh Admission, Due Admission, Urgent Admission, Urgent Order, Prioritised Matters, For Dismissal). No statutory citations, no precedents cited, no quantum.
What did the court decide?
Continuation of ad-interim/interim orders already granted, conditional on removal of office objections within two weeks; matters otherwise listed forward per the schedule (administrative listing order; no merits adjudicated). ¶10