Vishnu Dashrath Panasare and Ors. v. the Collector , Pune and Ors.
Case brief
What is this about?
The High Court of Bombay in PIL 145 of 2018 directed the Collector to produce records regarding the acquisition of lands for the Ujani Dam. The Court ordered that if lands were returned after acquisition but before possession, a notification under Section 48 of the Land Acquisition Act, 1894, must have been issued. The Respondents were mandamused to comply within six months.
What did the court decide?
Mandamus issued to Respondent No.1 to call for records and comply within six months.