Rau Vithu Patil and Ors. v. the Collector, Kolhapur and Ors.
Case brief
What is this about?
Petitioners challenged non-decision on their rehabilitation claim under the Maharashtra Project affected Persons Rehabilitation Act, 1986. The court directed them to complete formalities and submit required information within four weeks., prompting a decision within the following six weeks. Provided the information, the respondents must decide the rehabilitation claim. Otherwise, the petition proc
What did the court decide?
Petitioners directed to submit all requisite information within four weeks; respondents to decide claim within six weeks thereafter if information is furnished.