Gerald Paul D Mello v. the Municipal Corpn. of Gr. Mumbai
Case brief
What is this about?
This court quashed an order dated 18 April 2007 issued by an Executive Engineer without reasons, holding it violated natural justice under Article 226 and directed the respondent to pass an order afresh within four weeks with reasons.
What did the court decide?
The order dated 18 April 2007 passed by the Executive Engineer is quashed; the respondent is directed to pass an appropriate order afresh within four weeks after recording reasons.