Basireddy Penchal Reddy, v. The State of Andhra Pradesh
Case brief
What is this about?
Writ of mandamus; survey and boundary fixation of agricultural lands; land acquisition compensation under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013; failure to act on representation dated 19-03-2025; notice dated 28.12.2024 (Ex.P4) for survey on 07.01.2025; time-bound direction to revenue survey officials (respondents 6 to 8) to complete survey within eight weeks; compensation to be considered based on survey report; disposal at admission stage without touching merits, with consent; Article 226; Articles 14, 21, 300A; Section 151 CPC (interim applications); YSR Kadapa; National Highways Authority of India; no costs. Relevant for: scope of directions to survey authorities pre-adjudication; sequencing of compensation consideration post-survey under the 2013 Act.
What did the court decide?
Respondents 6 to 8 directed to complete survey of the petitioner's lands (Sy.Nos. 260, 262, 310, 311, 314/1, 353, 360, 372/1, 373/1, Mudumala Gram Panchayat, Chinnayapalli, B. Mattam Mandal, YSR Kadapa District) within eight (08) weeks from receipt of a copy of the order; based on the survey report, respondent authorities to consider payment of compensation, if any, payable to the petitioner; no order as to costs; as a sequel, pending miscellaneous petitions, if any, stand closed.