National Highway Authority of India Thru. Project Director v. Nirbay Pandey and Others
Case brief
What is this about?
Court-fees sufficiency verification and listing deferral; Appeal Under Section 37 Arbitration and Conciliation Act 1996 No. - 77 of 2024; appellant National Highway Authority of India thru. Project Director, counsel Sarvesh Kumar Dubey; respondents Nirbay Pandey and Others, counsel C.S.C.; Hon'ble Rajnish Kumar, J.; order date 15.1.2025; office-report dated 10.01.2025 (Rs. 240/more court-fees required); court-fees of Rs. 280/- deposited 12.01.2025; office to verify sufficiency; listed week commencing 27.01.2025; digitally signed by Anuj Nigam; High Court of Judicature at Allahabad, Lucknow Bench, Court No. 4.
What did the court decide?
No adjudicative relief granted; court-fees sufficiency left to office verification and the matter was listed for the week commencing 27.01.2025. ¶8