M/S. Adya Builders and Developers v. The State of Telangana
Case brief
What is this about?
Electricity connection mandamus; TGSPDCL; 12 domestic connections; total domestic load 60000 watts; Reg. No. LTM256490007; Gokul Plots, Hafeezpet, Venkataramana Colony, Serilingampally, Ranga Reddy District; GHMC Circle 20; disposed at admission stage; fresh application within one week; consideration in accordance with law preferably within two weeks; covered by order dated 12.02.2025 in W.P. No.4056 of 2025; Article 226 Constitution of India; section 151 CPC IA; no order as to costs; Justice Surepalli Nanda; Telangana High Court; 03.03.2025.
What did the court decide?
Writ petition disposed of at the admission stage: petitioner directed to make a fresh application with all relevant documents within one week; respondents to consider the application for 12 domestic connections (total load 60,000 watts) in accordance with law, preferably within two weeks thereafter. No order as to costs; pending miscellaneous petitions, if any, stand closed.