Koppuravuri Aswini v. The State of Telangana
Case brief
What is this about?
Petitioner sought a mandamus directing electricity distribution companies to process and release service connections to her plot in Gachibowli. Counsel submitted the issue was covered by an earlier order in W.P.No.9889 of 2024; respondents did not dispute this. The court disposed of the petition at admission stage, directing a fresh application to be considered within two weeks.
What did the court decide?
Direction to file fresh application within two weeks; respondents to consider grant of electricity connection and pass orders within two weeks thereafter; no costs.